1997
01.04.1997
The first of the two caissons for the pylons are towed to their allotted position and immersed into a 17 m deep hole dredged in the seabed.
16.07.1997
The floating crane, "Svanen" moves the first of the 51 bridge piers from Sundlink´s site in Malmö North Harbour to its destination at abutment of the bridge at Lernacken.
08.08.1997
The first of the 55,000 ton tunnel elements is towed from the tunnel factory at Copenhagen North Harbour to the tunnel trench in the Drogden channel.
27.09.1997
The Öresund motorway between Amager and Copenhagen Airport opens to traffic.
03.11.1997
The first of the 49 bridge sections for the approach bridges are shipped from Dragados Offshore yard in Cadiz to Sundlink´s site in Malmö.