1999
06.01.1999
The 20th an final tunnel element is placed in the tunnel trench.
18.01.1999
The first of the Öresund Bridge´s four pylon legs reaches its final height - 204 m.
The pylons are Sweden´s highest man-made structure.
16.03.1999
The few remaining meters of the tunnel alre completed,
enabling the first vehicle to drive through the tunnel.
14.08.1999
The final section is placed in position, completing the Öresund Link.
01.12.1999
The first railway track between Malmö and Copenhagen is completed.